SCP 514 - Amendment to SCP 496 Implementation Approach

  • CP Number SCP 514
  • Proposing Company E.ON ENERGY SOLUTIONS LIMITED
  • Raised Date 05/05/2021
  • Expected Implementation Date 25/06/2021
  • Implementation Date 25/06/2021
  • Impacted Parties All Suppliers,
  • Status Implemented
  • Urgent No
  • Last Updated 25/06/2021
  • Authority Consent Required? No
  • Change Proposer Kirsty Dudley
  • Synopsis

    This Change Proposal seeks to amend the implementation of SCP 496 ‘Maintaining Meter Asset Provider identities by Meter Asset Managers’ to a phased implementation with the governance as of June 2021 but the system changes aligned to the CDSP delivery in November 2021.

Raised
Issued In Change Pack
Issued to Impact Assessment
Voting
Awaiting Appeals window closure
Awaiting Implementation
Implemented